News Flash

Home

Posted on: November 6, 2020

2nd Avenue Bridge Replacement Project Updates

2nd Ave bridge - August 2020_1, credit RockSol

This project will replace the existing 2nd Avenue bridge over St. Vrain Creek to better accommodate future flood events. The bridge is closed to all traffic, including vehicle, pedestrian, and cycling, through May 2021. The 2nd Avenue alley access from 2nd Avenue is also closed. 

Access to 207 – 215 and 403 2nd Avenue is provided through a new permanent alley at 221 Park Street. Access to194 and 196 2nd Avenue is provided through a temporary alley access constructed on Town property located at 117 Park Street. Refer to the maps below.

2nd Avenue Road Closures and Detour Map >>

Trail Closures and Detour Map >>

2nd Avenue Alley Access Map >>

Please stay away from the construction zone. They have large equipment and cannot always see you! Thanks.

What's happening this week? (5/17-5/21)

Continue Park Street / 2nd Avenue intersection work
Continue bridge work
Prepare for and place asphalt pavement
Place 2nd Avenue sidewalk
Form and pour walls

What’s coming in the next few weeks? (Late May/early June 2021)

Form and pour walls
Construct paths
Place seeding and stabilization
Install final striping
Finishing work

Schedule

December 2020 - Constructed new 2nd Avenue alley access, closed 2nd Avenue bridge and 2nd Avenue alley, demolished bridge
January 2021 - Built a new storm sewer system, constructed retaining walls, installed erosion control and bridge protection (rip rap), backfilled bridge abutments.
February 2021 - Set bridge girders, constructed retaining walls, built trail underneath bridge, placed embankment material.
March 2021 - Anticipated work: pour bridge deck, install bridge railing, complete 2nd Avenue and Park Street intersection reconstruction except for final paving and permanent striping.


Traffic Impacts 
2nd Avenue will be closed to all traffic at St. Vrain Creek for approximately six months, from December 2020 through May 2021. The Park Street / 2nd Avenue intersection is also closed for several months for full reconstruction. Access to Bohn Park and the Recycling Center is possible from the south side of the bridge. Please follow the detour route utilizing U.S. 36 and McConnell Drive to access properties on either side of the bridge. 

All work is weather-dependent and the schedule is subject to change.

Background
Heavy rain and flooding in September 2013 caused debris to build up around bridge piers and water to breach the banks of the St. Vrain Creek. The flood event caused bridge scouring, erosion, and significant damage to infrastructure downstream. The Town was awarded FEMA mitigation funds to build a new single-span bridge designed to handle 100-year flood events. The new bridge will be longer and taller to eliminate obstructions and accommodate design flow rates.

Bridge work includes removing channel sediment, debris, and the damaged bridge structure. Construction will require installing cofferdams in the creek, excavating trenches for reinforced concrete footings, driving steel piles, and compacting backfill materials. Bridge approach work includes removing and replacing asphalt, curb and gutter, sidewalk, pavement structure, storm systems, bridge abutments, and signing and striping.

Zak Dirt Inc. was awarded the construction contract for $3.3 million by the Board of Trustees on September 8, 2020.

2nd Ave. Bridge Site Plan >>
With questions, please contact Flood Recovery Manager, Tracy Sanders.

Project Progress Photos

1. 2nd Ave bridge - August 2020_1, credit RockSol

2. 2nd Ave bridge - August 2020_2, credit RockSol

4. Before - bridge deck

6. Before - bridge under
5. Before - bridge side

8. Bridge demo side

10. Bridge demo deck


Facebook Twitter Email

Other News in Home

Arielle Hodgson, Black Bear Hole  2

Rainbows Need Rain!

Posted on: May 12, 2021
Main St_c1910

May- Full of Promise and Flowers!

Posted on: May 7, 2021
You Can Make a Difference

You Can Make a Difference in Lyons!

Posted on: April 15, 2021
Poetry Contest Image

Dear April

Posted on: April 5, 2021
Arielle Hodgson, Black Bear Hole  2

Finding Joy in Lyons

Posted on: March 27, 2021
be_someones sunshine

Be Someone's Sunshine!

Posted on: March 22, 2021
snow-family

Ch-Ch-Changes

Posted on: March 16, 2021
steamboat mtn before storm

Prepping for Old Man Winter

Posted on: March 12, 2021
Smile You're in Lyons

Mother Nature & Old Man Winter

Posted on: March 10, 2021
DSCN3467

Happy FriYay Lyons!

Posted on: March 1, 2021
___TOL No Background 400small

2nd Ave Bridge Construction Update

Posted on: February 8, 2021
DSCN3467

Have a Super Week Lyons!

Posted on: February 7, 2021
LYONS_GetSomeLyons_skating

Where'd You Go January?

Posted on: February 1, 2021
___TOL No Background 400small

The Sky is a Hazy Shade of Winter

Posted on: January 22, 2021
LYONS_GetSomeLyons_skating

Well Hello 2021!

Posted on: January 10, 2021
thank_you_firefighters

How 'Bout Some Good News Lyons?

Posted on: October 29, 2020
2020SpooktacularPoster_greenv2_outline

2020 Halloween Spooktacular

Posted on: October 9, 2020
2020SpooktacularPoster_greenv2_cropped2

Lyons, Tigers, and Halloween!

Posted on: October 9, 2020
Library_CreativeOutlet_1

It's Hot. Then It's Not!

Posted on: September 4, 2020
Schedule Overview Map

Raw Waterline Project

Posted on: July 16, 2020
Milling and Paving

Flood Recovery Milling and Paving

Posted on: May 6, 2020
Sunset_Bohn Park

Is that you, Summer?

Posted on: June 19, 2020
Bear at Roussills

Be Bear Aware - Help Keep Bears Wild

Posted on: July 10, 2019
Recycling Guidelines

Recycling Center Guidelines

Posted on: February 6, 2019
Golf Carts & LSEVs

Golf Carts in Lyons

Posted on: February 5, 2019